August 2021 Update
The site contractor (Marfleet and Blythe) has now undertaken, initial drainage connection works on the Railway section of the site.
Both the Railway and Garage sections of the site have now been secured.
Demolition of the garage site by the main contractor, is due to commence early August. This forms the start of the program of works, which is due for practical completion in early April 2022.
Marfleet and Blythe, will be distributing updates to the residents in due course.